CruOps National Deployment Timeline
|
Target Date |
Task |
|
July 3 |
CruOps Oracle
alpha software complete/Alpha testing begins |
|
July 7-25 |
Conduct NATCA
Reps/Mgmt Focal training |
|
July 7 |
SISO Appliance
delivery begins, emphasis on key sites |
|
July 17 |
CruOps Alpha testisg
complete |
|
July 18 |
Deliver CruOps
software to ATX-100 for CBI finalization |
|
July
18 |
Release CruOps Deployment Guide to facilities/I&I begins |
|
August 18 |
ATX-100
completes CruOps CBI |
|
August 19 |
--Upon receipt
of CBI, keysite/facilities begin training --Beta software
available for facilities --As soon as
each site completes training, keysite testing
begins |
|
September 22 |
Deadline for
initial local I&I |
|
October 3 |
Deadline for CruOps SISO hardware installation at all facilities |
|
October
29 |
Finalize CruOps Key Site testing no later than… |
|
October 29 |
CruOps General Release available to all
facilities through download |
|
November 29 |
All facilites have CruOps software
installed and configured |
|
January 1, 2004 |
CBI training
complete at all field facilities |
|
January 30, 2004 |
National CruOps deployment complete |
After hardware and
software installation are complete and training is complete, facilities are
expected to transition. This transition
must take place no later than the National deployment date of January 30, 2004.